METRO - Lime Street - London Road - Monument Place - Low Hill consultation
Results updated 7 Jul 2026
Following the summer 2025 consultation we are holding a series of events to share the final designs and concepts:
Thursday 9th July: Liverpool Central Library (Discover Room), William Brown Street, L3 8EW. Time: 4.30 - 7.30pm.
Friday 10th July: Royal Liverpool Hospital, (Ground floor atrium), Mount Vernon Street, L7 8YE. Time: 11am - 3pm.
Saturday 10th July: Liverpool Central Library (Discover Room), William Brown Street, L3 8EW. Time: 10am - 2pm.
Tuesday 14th July: The Brain Charity (The Lounge Room), Norton Street, Liverpool, L3 8LR. Time: 1 - 5pm.
All welcome to join us and tell us your thoughts.
You can see the new designs and read about them by clicking on the document links below;
Files:
- Easy read guide to new plans, 81.9 KB (Office Word 2007 XML document)
- New Design plans, 31.4 MB (PDF document)
Overview
Liverpool City Region Combined Authority and Liverpool City Council have put together ambitious plans to improve walking, wheeling, cycling and bus links between Liverpool city centre, the lively Fabric District and beyond.
Running along London Road and Prescot Street towards Low Hill, the planned scheme features:
- Improved footpaths and road crossings
- New segregated cycle lanes
- Measures designed to reduce journey times for buses, such as new bus lanes and upgraded junctions
- Improved public plaza at Monument Place including new seating, outdoor events space and open bandstand
We encourage local residents and transport users to give feedback on the proposals as to whether improvement measures would make it easier to access facilities / specific locations using active travel and bus, and / or improve health and wellbeing.
Either complete our survey or attend one of the two events as featured below, where you'll also find a link to our Frequently Asked Questions document.
What happens next
Once the survey is closed we will review responses which will then will inform the next stage of the design.
The provisional timeline of the scheme looks like this:
- Assess consultation feedback and report - Autumn 2025
- Detailed design - 3 months, complete late 2025
- Construction contractor procurement - 4 months
- Construction period - mid 2026 for 12-18 months
Events
-
DoES Liverpool, Events Room, 1st floor, The Tapestry Building, Fabric District
From 17 Jun 2025 at 15:00 to 17 Jun 2025 at 19:0068-76 Kempston Street
Liverpool L3 8HLCome along and see the proposals on large boards, chat to our team and complete the survey. Secure cycle parking on corner of Gildart Street
-
Central Library, Liverpool (Discover Library)
From 28 Jun 2025 at 10:00 to 28 Jun 2025 at 14:00William Brown Street, Liverpool L3 8EW
Based in the Children's & Family Library on the ground floor.
Come along and see the proposals on large boards, chat to our team and complete the survey.
Areas
- All Areas
Audiences
- General Public
Interests
- Bus
- Cycling
- METRO Network improvements
- Walking
- Wheeling
Share
Share on Twitter Share on Facebook